View the works locations
Duration: 23 November 2020 – 10 December 2020.
Impact: Minor distributions, traffic control will be implemented.
Contact: Wayne Ballinger on 0405 688 343.
Works: Installation of Christmas decorations, street frames, baubles and banners.
Duration: Monday 23 November to Friday 4 December 2020.
Impact: Minor disruption to traffic and pedestrians whilst Christmas decorations are installed. Please observe signage and traffic controls
Works: Concrete repair and corrosion protection to the underside of the bridge deck.
Duration: Approximately 14 weeks from Monday September 21.
Impact: Interruptions to pedestrian access and bicycle lane. Vehicular traffic may be disrupted.
Contact: Don Allen, Construction Engineer on 0419 389 638.
Lady Bay Beach (ESTA WCC124 McGennans Carpark & WCC131 Surfside Holiday Park)
Works: Construction work for the replacement beach access infrastructure.
Duration: Up to 6 weeks from Wednesday September 30.
Impact: Closure of both beach access and partial section of McGennans Carpark. Promenade to remain open to public. Intermittent closure of ESTA WCC127 Warrnambool SLSC to transport materials and equipment along the beach to the work sites.
Contact: Jen Macmillan, Infrastructure Project Officer on 5559 4800.
Wangoom Road
Works: Shoulder widening on Wangoom Road between Aberline Road and Horne Road plus an upgrade to the Wangoom/Aberline Road intersection including new street lighting.
Impact: Some disruptions to traffic including intermittent lane closures. Please observe signage.
Duration: Approximately six months commencing Monday August 31.
Contact: Jackson Fary, 0428474 676.
Wollaston Heritage Footbridge
Works: Turret caps replacement and installation of barrier infill.
Duration: Week commencing Monday 2 November 2020 for 6 weeks.
Impact: Vehicular traffic will not be disrupted, however pedestrian traffic may be affected. Motorists and pedestrians are advised to observe all signage.
Contact: Don Allen, Construction Engineer on 0419 389 638.